Methodology
Quality Assurance
Processes
 
Deployment
Purpose Beta test and evaluate the site, launch the site, move site ownership to the supporting organization, conduct a Project Completion Review, and perform a project debriefing to gather lessons learned.
Tasks Included Launch beta site and perform performance tests.
Provide training and implement organizational changes.
Launch the site.
Transition ownership to the supporting organization.
Conduct Project Completion Review.
Perform project debriefing.
Output Artifacts Completed system test documentation
Fully tested and launched site
Associated Documents Project Configuration Worksheet
Project Debriefing Worksheet
Site Submission and Promotion resources
Completion Criteria Successful site beta test and launch based on predefined success criteria.
Copyright © 2002-2007 VeriPark All rights reserved. | Privacy Policy
Discovery
Analysis
Design
Development
Deployment
Operation